TY - JOUR ID - TI - Entropy Method as Criteria for Analysis of a Steam Power Plant AU - Moayed Razoki Hasan PY - 2007 VL - 13 IS - 3 SP - 1818 EP - 1833 JO - Journal of Engineering مجلة الهندسة SN - 17264073 25203339 AB - In this paper a theoretical analysis of South Baghdad and Dura power plant is carried out according to second law of thermodynamic depending on entropy (irreversibility coefficient or lost work) method instead of exergy (availability) method. In the used entropy method. The power plant is divided into main blocks ( boiler, turbine, condenser, and feed water heater and pumps ). The irreversibility losses and coefficient for each block are calculated and then the overall irreversibility and thermal efficiency of the plant are calculated. The results of this work are compared with previous results, that depending on exergy method. The comparison of results show that both methods give approximately the same results since both of them rely the 2nd law of thermodynamic. Entropy method is simple and intellectually and intuitively satisfying and giving direct relationship between components losses of power plant and its overall efficiency.

يتناول البحث الحالي تحليل محطة جنوب بغداد ومحطة الدورة الحرارية باعتماد طريقة الانتروبي (معامل اللانعكاسية او الشغل المفقود) بدلا من طريقة المتاحية. في طريقة الانتروبي المستخدمة, يتم تقسيم محطة القدرة الى اجزاء رئيسية ( المرجل, التوربين, المكثف, و المسخنات و مضخات ماء التغذية ). يتم حساب معاملات و خسائر اللاانعكاسية لكل جزء ثم بعد ذلك يتم حساب اللاانعكاسية الكلية للمحطة و كفاءتها الحرارية. اظهرت مقارنة النتائج مع نتائج الاعمال السابقة لتحليل المحطتين باعتماد طريقة المتاحية. لقد اشارت النتائج بان الطريقتين تعطيان نتائج متقاربة جداً مع افضلية لطريقة الانتروبي التي تمتاز بسهولتها مع امكانية الربط المباشرلخسارات كل جزء من اجزاء المحطة مع الكفاءة الكلية للمحطة. ER -